I use this page to make available documents that I am sharing with colleagues or students involved with me on a current project – you know who you are. Look down the page for the project name, and then look down for the document name and click on it to access the document. If you expected a document to be here and you cannot find it, please contact me. If there are no documents whatsoever listed, … then there are no documents listed.
|
||||
|
Materials for course on Financing Energy Investments
|
||||
| Du, Yangbo and John E. Parsons, "Update on the Cost of Nuclear Power," Center for Energy and Environmental Policy Research Working Paper #09-004, May 2009. link: http://web.mit.edu/ceepr/www/publications/workingpapers/2009-004.pdf |
||||
| spreadsheet to accompany Du and Parsons link: http://web.mit.edu/ceepr/www/publications/workingpapers/Du%20and%20Parsons%20update%20cost%20of%20nuclear%2009%2005%20rev3.xls |
||||
| Joskow, Paul, Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies, Center for Energy and Environmental Policy Research Working Paper #10-013,
September 2010.
link: link: http://web.mit.edu/ceepr/www/publications/workingpapers/2010-013.pdf |
||||
| Lecture Slides, Discounted Cash Flow, Monday, March 18. PPT | ||||
| E.ON Annual Report for 2010.
|
||||
| Constellation Energy Investor Presentation 2006.
|
||||
| McKinsey Co., Determining appropriate WACC for NorNed Investment, June 2004.
|
||||
| Brealey, Richard, Richard Caldwell and Carlos Lapuerta, The Cost of Capital for the Nor-Ned Cable, The Brattle Group, June 2004.
|
||||
| Lecture Slides, Risk & the Cost of Capital, Tuesday, March 19. PPT | ||||
| CBO (2011) Federal Loan Guarantees for the Construction of Nuclear Power
Plants.
|
||||
| Lecture Slides, Risk & Leverage (corrected), Wednesday, March 20. PPT | ||||
| Hand-In Assignment #1, Spreadsheet. XLS | ||||
| Brealey et al. (1996) Using Project Finance to Fund Infrastructure
Investments
|
||||
| Lecture Slides, Project Finance, Thursday, March 21. PPT | ||||
| Parsons (1989) Estimating the strategic value of long-term forward purchase
contracts using auction models.
|
||||
| Hall and Parsons (1990) The efficient design of contracts to purchase
cogenerated power.
|
||||
| Hampson et al. (1991) A case study in the design of an optimal production
sharing rule for a petroleum exploration venture
|
||||
| Lecture Slides, Risk Management, Friday, March 22. PPT | ||||
| Mello and Parsons (1999) Strategic Hedging
|